Progress of Jaffery masjid, Masongaleni
21st September 2011
Salaamun alaykum,
Re: Jaffery Masjid, Masongaleni
Report of the Masjid Works to date:
Progress Report:
-
The roofing truss and the roofing sheets are fitted
- Plastering of the Masjid internally and externally is done.
- The contractor has placed orders for wooden doors and windows in Mombasa as per our specification.
- The contractor is working on the iron grilles to be placed at the entrance wall.
- Crenellations in the front and entrance are in place.
- Alhamdullilah during the Idd Ul Fitr the prayer area was cleared and the community prayed Idd prayers.